CASE STUDIES

COMMISSIONING

 

NYU Winthrop Hospital

HVAC Commissioning of Ambulatory Surgery Center
Mineola, NY

 

Construction HVAC commissioning for Ambulatory surgery center that includes six (6) operating rooms (approximately 14,000 sq.ft).

Commissioning activities started from the construction phase to post acceptance phase.  Review construction correspondence (RFI’s, responses, change orders) pertinent to commissioned equipment and systems. Prepared commissioning plan and carried out system verification checklist, functional performance tests, provide unscheduled and scheduled site visits, record, issue and update issues log, organize commissioning meetings between all interested parties and carried out off-season tests. Observe duct and piping pressure testing, attend and record maintenance personnel training sessions and issue a final commissioning report. Final report to include systems manual including start-up, emergency shut off, recommendation and description of energy saving strategies, recommendations for re-commissioning frequency by equipment type, etc.

 

Contact

Contact Lizardos

Twitter Facebook

LinkedIn YouTube Google Plus

Careers

Visit our career pages for updated careers

Services

Mechanical
Electrical
Plumbing
Central Utility Plant Design
Site Infrastructure
Sustainability
Building Management
Commissioning
BIM
Industrial
Construction